Depot Report - Sunday 6th December 2021



No.8s Cab - Two jobs on the cards today the first being returning to the cab floor. The floorboards have now been marked out and are now all screwed down, a couple of boards also have the trims fitted too. The other trims will be fitted at some point in the next few weeks once we have some new lengths of trim ordered to replace a couple of pieces that are missing or damaged.



The second job involved unboxing a delivery of 2 horns kindly sent to us from our friends at The South Wales Loco Cab Preservation Group, so a huge thank you to them for their help. The horns were firstly stripped down and given a good clean up, once all the parts were clean the back sections were rebuilt, and all given a coat of primer.