Depot Report 12/4/25


Depot report 12/4/25.

A very productive day at Barrow Hill.

The delectricians were busy refurbishing relays and other equipment as they build up a supply of serviceable spares.

On PU 430 work continued preparing the unit for reassembly including refitting the crankcase cover for C bank.

D9015.

The replica works plates were fitted.

55009.

Just a small amount of welding to go with the body repairs now. The perspex head code discs were fitted at #2 end and this end is now almost complete.

Work continued in the stores preparing the new racking.


 
 
 